The following job list and schedule to build a single module is based on a crew of 4-6 people. This is provided to give you a general sense of the ease of construction in building a Weekend Warrior cabin. The project schedule is based on the premise that the foundation and sub-floor is in place prior to the first weekend of the construction schedule. In addition, it is assumed that the material and mechanical / electrical contractors deliver on time.
|
Weekend Warrior - 1st Weekend |
Friday P.M. |
pre-fabricate walls, measure and cut loft floor joists |
Saturday A.M. |
erect walls, install loft floor joists and sub-floor |
Saturday P.M. |
install roof trusses, sheathing, box in chimney, install
roofing material and exterior building paper |
Sunday |
install windows and exterior doors, install fascia and soffits |
* co-ordinate mid-week the electrical and plumbing installations |
|
Weekend Warrior - 2nd Weekend |
Friday P.M. |
insulate walls, ceiling and install vapour barrier |
Saturday |
install drywall |
Sunday |
1 crew: mudding and taping / 1 crew: canopy installation |
|
| Weekend Warrior - 3rd Weekend |
| Friday P.M. |
apply second coat of mud |
| Saturday A.M. |
1 crew: apply third coat of mud / 1 crew: install siding |
| Saturday P.M. |
1 crew: final sanding / 1 crew: install siding |
| Sunday A.M. |
1 crew: prime and paint / 1 crew: install siding |
| Sunday P.M. |
1 crew: second coat of paint / 1 crew: install siding |
| |
| Weekend Warrior - 4th Weekend |
| Friday P.M. |
paint touch-ups, pre-paint base boards, door and window trim |
| Saturday |
hang interior doors, install cabinets and millwork |
| Sunday |
install flooring, baseboards and plumbing fixtures |
| |
celebrate the completion of your Weekend Warrior cabin |
| * based on the premise that the celebration occurs after completion |